With the rapid development of IT technology, the questions in the IT certification exam are also changing. Therefore, ITCertKing also keeps updating test questions and answers. And if you purchase ITCertKing PMI PMI-001 practice test materials, we will provide you with free updates for a year. As long as the questions updates, ITCertKing will immediately send the latest questions and answers to you which guarantees that you can get the latest materials at any time. ITCertKing can not only help you pass the test, but also help you learn the latest knowledge. Never pass up a good chance to have the substantial materials.
ITCertKing provides a clear and superior solutions for each PMI PMI-001 exam candidates. We provide you with the PMI PMI-001 exam questions and answers. Our team of IT experts is the most experienced and qualified. Our test questions and the answer is almost like the real exam. This is really amazing. More importantly, the examination pass rate of ITCertKing is highest in the worldwide.
Exam Code: PMI-001
Exam Name: PMI (Project Management Professional V5)
One year free update, No help, Full refund!
Total Q&A: 600 Questions and Answers
Last Update: 2014-02-24
Only to find ways to success, do not make excuses for failure. To pass the PMI PMI-001 exam, in fact, is not so difficult, the key is what method you use. ITCertKing's PMI PMI-001 exam training materials is a good choice. It will help us to pass the exam successfully. This is the best shortcut to success. Everyone has the potential to succeed, the key is what kind of choice you have.
If you attend PMI certification PMI-001 exams, your choosing ITCertKing is to choose success! I wish you good luck.
Now passing PMI certification PMI-001 exam is not easy, so choosing a good training tool is a guarantee of success. ITCertKing will be the first time to provide you with exam information and exam practice questions and answers to let you be fully prepared to ensure 100% to pass PMI certification PMI-001 exam. ITCertKing can not only allow you for the first time to participate in the PMI certification PMI-001 exam to pass it successfully, but also help you save a lot of valuable time.
PMI-001 Free Demo Download: http://www.itcertking.com/PMI-001_exam.html
NO.1 Which of the following factors are NOT included in cost control?
A. Preparation of cost estimates.
B. Informing stakeholders of changes.
C. Monitoring cost performance.
D. Recording appropriate changes to the cost baseline.
Answer: A
PMI questions PMI-001 test PMI-001 certification
NO.2 In which of the following circumstances is it BEST to make use of the project
management approach? (Choose all that apply.)
A. Cross functional tasks.
B. Unique operations.
C. Product manufacturing environment.
D. Time-constrained deliverables.
E. Production-line environment.
Answer: A, B, D
PMI PMI-001 PMI-001 pdf PMI-001
NO.3 Which of the following is NOT an essential regarding a project close-out?
A. Documenting formal acceptance of the product.
B. Documenting the final risk assessment.
C. Documenting the lessons learned.
D. Documenting the final project scope
E. None of the above.
Answer: B
PMI PMI-001 PMI-001 PMI-001 exam simulations PMI-001 demo
NO.4 Which of the following is NOT an indirect cost?
A. Insurance costs.
B. Payroll tax cost.
C. Subcontract costs.
D. Accounting support costs.
Answer: C
PMI PMI-001 braindump PMI-001 PMI-001 certification training PMI-001 PMI-001
NO.5 When preparing the probability distribution of cost outcomes for a project, what is
the estimate with a 15% probability of being exceeded approximately one standard
deviation ___________?
A. Above the mean.
B. Below the mean.
C. Below the median.
D. Above the median.
Answer: A
PMI PMI-001 PMI-001 test answers PMI-001 exam dumps PMI-001 PMI-001
NO.6 Which of the following statements BEST describes what project progress reports
are?
A. It is used to predict future status and progress.
B. The project sponsor makes the most use of it.
C. It is an important communications element.
D. It is needed on a weekly basis.
Answer: C
PMI exam simulations PMI-001 braindump PMI-001 PMI-001 exam prep PMI-001 dumps
NO.7 Taking the following table into account, where would corrective action be MOST
effective when you make use of Pareto's Rule?
Origin of Problem Percent of Problems
Design 60
Development 15
Prototype 10
Testing 10
Fabrication 5
A. Development
B. Prototype
C. Fabrication
D. Design
E. Testing
Answer: D
PMI PMI-001 PMI-001 test questions
NO.8 Which of the following are indicative of duration estimates?
A. How many hours a resource will work on an activity.
B. When an activity is expected to start.
C. How many work periods an activity is expected to last.
D. When an activity is expected to finish.
Answer: C
PMI PMI-001 pdf PMI-001 PMI-001 PMI-001
NO.9 Which of the following represents the BEST process to accomplish resource
planning?
A. Identifying the required resources in the project charter
B. Identifying the available resources and allocate them to all activities in the current
phase of the project.
C. Identifying the required resources and allocate them to all project activities.
D. Identifying the resources that performed past similar projects, and allocate them to all
project activities
E. None of the above
Answer: C
PMI PMI-001 test answers PMI-001 PMI-001 pdf
NO.10 What does a benefit-cost ratio of 3.22 indicate?
A. A profit of s3.22 per unit produced.
B. A payback of s3.22 for each dollar expended.
C. The percentage of resources assigned to other tasks on the critical path.
D. The gold plating result.
E. A profit of s3.22 for each dollar expended.
Answer: B
PMI dumps PMI-001 test questions PMI-001 PMI-001 PMI-001 PMI-001 exam prep
NO.11 The "Cost of quality" project management concept includes ____?
A. The costs involved when changes are made to the requirements
B. The costs of ensuring that requirements are conformed to.
C. The costs incurred when requirements are exceeded.
D. The costs involved with quality control requirements.
Answer: B
PMI test answers PMI-001 PMI-001 practice test PMI-001
NO.12 Which of the following is illustrated by a resource histogram?
A. The expected requirements for critical path activities.
B. The expected resource usage by time period.
C. The resource assignments by work package.
D. The resource assignments by activities.
E. All of the above.
Answer: B
PMI original questions PMI-001 PMI-001 PMI-001 PMI-001
NO.13 What is the job title of the person who is primarily responsible for the quality of
deliverables?
A. The quality control inspector.
B. The quality controller.
C. The design engineer.
D. The project manager.
E. The quality manager.
Answer: D
PMI PMI-001 dumps PMI-001
NO.14 Which of the following are included in cost control? (Choose all that apply.)
A. Informing stakeholders of changes.
B. Preparing cost estimates.
C. Recording appropriate changes to the cost baseline.
D. Monitoring cost performance.
Answer: A, C, D
PMI PMI-001 demo PMI-001 dumps PMI-001
NO.15 What would be the cost performance index if BCWP =350, ACWP = 400, and BCWS = 325? Note:
Budgeted Cost of
Work Performed (BCWP), Actual Cost of Work Performed (ACWP) and Budget Cost of Work Schedule
(BCWS)
A. 0.813
B. 1.078
C. 1.143
D. 0.875
Answer: D
PMI answers real questions PMI-001 braindump PMI-001 test questions PMI-001
NO.16 Which of the following describes Fast Tracking?
A. Circumventing loopholes.
B. Developing workarounds for previous problems.
C. Increased project risk.
D. Getting people to work longer hours in overtime.
E. Meeting schedule objectives by adding resources.
Answer: C
PMI pdf PMI-001 practice test PMI-001 exam
NO.17 Which of the following is NOT included in activity duration estimated?
A. Project team knowledge.
B. Commercial duration databases.
C. Time studies.
D. Information from previous experience.
E. None of the above.
Answer: C
PMI PMI-001 dumps PMI-001 exam dumps PMI-001 demo
NO.18 Which of the following represents the pinnacle of Maslow's hierarchy of needs?
A. Survival.
B. Self-actualization.
C. Safety.
D. Esteem.
E. Physiological satisfaction.
Answer: B
PMI PMI-001 PMI-001
NO.19 Which of the following should be done by the project manager upon completion of
the project?
A. Planning a turnover meeting.
B. Obtaining a sign-off from the customer.
C. Team celebration.
D. Project evaluation.
E. Performance evaluation of team members.
Answer: B
PMI answers real questions PMI-001 PMI-001
NO.20 Where does comparing actual to baseline schedules, examining the statement of
work, understanding cost overruns, and assessing risk all occur?
A. Stakeholder meeting.
B. Resource leveling activity.
C. Project audit.
D. Contract negotiation.
Answer: C
PMI answers real questions PMI-001 PMI-001 PMI-001 exam
NO.21 Under which of the following circumstances would project management is the NOT
be the preferred management approach?
A. Cross functional tasks.
B. Unique operations.
C. Product manufacturing environment.
D. Time-constrained deliverables.
Answer: C
PMI exam simulations PMI-001 PMI-001
NO.22 Which technique would you be using if you analyze which sequence of activities has
the least amount of flexibility when you need to predict project duration?
A. Critical path
B. Dependency diagramming
C. PERT
D. Gantt chart
E. Monte Carlo method
Answer: A
PMI PMI-001 test questions PMI-001 PMI-001 exam dumps
NO.23 Which of the following requires an expenditure of the resources when working
within an arrow diagramming method?
A. Histograms.
B. Accounting support costs.
C. Pareto diagram.
D. Milestone events.
E. Path activities.
Answer: B
PMI PMI-001 PMI-001 original questions PMI-001 PMI-001
NO.24 Certain resources have been added to tasks on the critical path so as to reduce the
project duration. As a result the plan should then be reviewed for the:
A. Possible lag time on other paths.
B. Resource assigned to other tasks on the critical path.
C. The most time consuming task remaining in the plan.
D. Emergence of a new critical path.
Answer: D
PMI PMI-001 certification training PMI-001 PMI-001
NO.25 Which of the following is the distinguishing characteristic between the network
diagram and the Gantt chart?
A. Few resources
B. Key milestones
C. Critical dates
D. Critical dependencies
Answer: D
PMI PMI-001 PMI-001 test answers PMI-001
NO.26 Which of the following statements depicts the key difference between contract
close-out and administrative closure?
A. Contract close-out formalizes project completion.
B. Contract close-out includes product verification.
C. Contract close-out includes updating records with final results.
D. Administrative closure includes procurement audits.
E. None of the above.
Answer: B
PMI answers real questions PMI-001 PMI-001 certification PMI-001
NO.27 Which of the following represents a consequence to the project in the event of a
resource being added to the project team during execution?
A. Shorter project completion schedule.
B. An indeterminable effect.
C. A requirement for a scope change.
D. An increase in project quality.
Answer: B
PMI dumps PMI-001 PMI-001 PMI-001 exam dumps PMI-001 practice test PMI-001 original questions
NO.28 Consider the following situation: The customer was given a monthly report that
indicates zero schedule variance. One of the teams members are aware of at least
one milestone that has not been achieved. This missed milestone will result in an
overall delay in the project.
Which of the following items were not reported on adequately?
A. Critical path status
B. Risk analysis
C. Communication plan variance
D. Resource management plan
E. All of the above
Answer: A
PMI certification training PMI-001 pdf PMI-001 PMI-001 dumps
NO.29 Which of the following is the MAIN reason for including incentive clauses in a
contract?
A. Reducing costs to the buyer.
B. Controlling contractor costs.
C. Aligning contractor and buyer goals.
D. Reducing production costs.
E. Reducing contractor risk.
Answer: C
PMI PMI-001 PMI-001 certification PMI-001
NO.30 Which of the following represents the final task during project close-out?
A. Reassignment of team member.
B. Verification that contractual obligations were met.
C. Transferring the deliverables to the client.
D. Completion of performance/lessons-learned records.
Answer: C
PMI PMI-001 PMI-001 questions
ITCertKing offer the latest 000-588 exam material and high-quality HP2-W100 pdf questions & answers. Our MSC-321 VCE testing engine and 000-087 study guide can help you pass the real exam. High-quality MSC-431 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.